3 men or 5 women can do a work in 12 days. How long will 6 men and 5 women take to do it?


Number of days required by 3 men to finish the work : 12 days


Number of days required by 5 women to finish the work : 12 days


Number of days required by 1 man to finish the work : 3 x 12 = 36 days


Number of days required by 1 woman to finish the work : 5 x 12 = 60 days


Work done by a man in one day:


Work done by a woman in one day:


Work done by 6 men in one day: 6 x =


Work done by 5 women in one day: 5 x =


Work done by 6 men and 5 women together in one day: + = =


6 men and 5 women together take 4 days to complete the work.