A and B can polish the floors of a building in 10 days. A alone can do th of it in 12 days. In how many days can B alone polish the floor?

Given,


A and B can polish a building in = 10 days


A alone can do of it in 12 days


(A+B)’s 1 day work =


A’s I day work =


B’s 1 day work = (A+B)’s 1 day work – A’s 1 day work =


Thus B can finish the work in = days.