A and B can do a piece of work in 20 days and B in 15 days. They work together for 2 days and then A goes away. In how many days will B finish the remaining work?

Given,


A and B can do a piece of work in = 20 days


B can do it in = 15 days


A and Bs 1 day work =


B’s 1 day work =


A and B work for 2 days, hence work done by them in 2 days =


Remaining work =


B do work in = 1 day


B do 1 complete work in =


B will do work in = days