A, B and C can do a piece of work in 10 days, 12 days and 15 days respectively. How long will they take to finish it if they work together?

Number of days A required do a piece of work : 10


Number of days B required do a piece of work : 12


Number of days C required do a piece of work : 15


Work done by A in one day:


Work done by B in one day:


Work done by C in one day:


Work done by A, B and C together in one day: = =


They can do the work together in 4 days .