A can do a piece of work in 14 days while B can do it in 21 days. They began together and worked at it for 6 days. Then, A fell ill and B had to complete the remaining work alone. In how many days was the work completed?

Number of days A required do a piece of work : 14 days


Number of days B required do a piece of work : 21 days


Work done by A in one day:


Work done by B in one day:


Work done by A and B together in one day: =


They can do the work together in days .


A and B worked together for 6 days, so work completed by A and B in 6 days :


Work left =


Number of days taken by B to complete the left over work : = 6 ( here 21 is days required by B to complete a piece of work).


Time taken to finish the work: 6 + 6 = 12 days.


Total time taken to finish the work: 12 days