To complete a work, A takes 50% more time than B. If together they take 18 days to complete the work, how much time shall B take to do it?

Let number of days B required a work be x


Then number of days A takes to complete the work is : = 1.5x


Work done by A in one day: =


Work done by B in one day:


Number of days taken by A and B to do the work together: 18 days


Work done by A and B together in one day:


That is : = +


=


X = = 30


B alone will take 30 days to complete the work.