To complete a work, A takes 50% more time than B. If together they take 18 days to complete the work, how much time shall B take to do it?
Let number of days B required a work be x
Then number of days A takes to complete the work is : = 1.5x
Work done by A in one day: =
Work done by B in one day:
Number of days taken by A and B to do the work together: 18 days
Work done by A and B together in one day:
That is : =
+
=
X = = 30
B alone will take 30 days to complete the work.