The following table gives the total product schedule of labour. Find the corresponding average product and marginal product schedules of labour.


L



TPL



0



0



1



15



2



35



3



50



4



40



5



48



L



TPL



AP



MP



0



0



0



0



1



15



15



15



2



35



17.5



20



3



50



16.67



15



4



40



10



10



5



48



9.60



8



MP – Marginal Product = TPN+1 - TPN


AP – Average Product = TP / L


22